Walk to the end of Sea Cliff Avenue on any clear morning and you will pass the same closed bathhouse you passed last year, and the year before that. Keep walking past Eagle Point onto the Lands End Coastal Trail and, within a mile, you will round the bluff to see the Cliff House still boarded up, its windows plywood, its famous sign still missing from the roofline where it hung for over a century. Both buildings have been "reopening soon" for so long that the phrase has become part of the neighborhood's background noise, something you register and stop registering, like the foghorns.
But something did actually change on this stretch of coastline in the last year, and it is worth understanding what and why, because the pattern behind the delays tells you more about what to expect next than any press release does.
Two Projects, One Landlord
The Cliff House and China Beach are separate buildings with separate operators and separate construction schedules, but they share a landlord: the National Park Service, which owns both sites as part of the Golden Gate National Recreation Area.
Work on federal land involves lease negotiations, historic preservation review, and procurement rules. The Cliff House has been closed since December 31, 2020. The reopening process has involved a lease, permits, a construction bid, materials, and repairs for deterioration from sea air. Announced target dates have changed several times.
The Cliff House's Fourth Deadline
The San Francisco Chronicle reported on the lease, building work, and name donation described below. The Cliff House first promised a 2022 reopening. That date slipped to 2024, then to 2025, and the current target has the coffee shop opening this summer with the rest of the building following by the end of the year. Attorney Alexander Leff, a Richmond District native operating under Sutro Lands End Partners, signed a 20-year lease with the National Park Service after years of negotiation, and has brought in Hi Neighbor Hospitality Group, the team behind 7 Adams, Trestle, and the Vault Steakhouse, to consult on the food program. The plan calls for four separate concepts inside the building: a casual, family-friendly spot with burgers and milkshakes on the back patio, a seafood-focused restaurant, a coffee and pastry counter in the old gift shop space, and a fourth concept not yet announced.
The construction estimate gives one measure of the project's scope. In 2024, restoring the building was projected to cost around $10 million. By the fall of 2025, that figure had climbed to somewhere between $20 and $25 million, as the extent of damage after five years of exposure to salt air and vacancy became clear: new elevators, a new HVAC system, a new roof, and structural repairs the National Park Service itself has acknowledged were needed by the time the previous long-term operators left.
One piece of the story did resolve cleanly, though. For years, it was genuinely unclear whether the building would even be allowed to reopen under the name Cliff House, since the Hountalas family, the 47-year operators of the restaurant, held the trademark. In November 2025, Dan and Mary Hountalas donated the name, the original recipes, the social media accounts, and the historic sign itself to the Western Neighborhoods Project, a small nonprofit founded in 1999 and based at 1617 Balboa Street that has spent years preserving the history of the city's west side. Executive director Nicole Meldahl's organization already has a track record here: in 2021 it raised $180,000 to buy more than a hundred Cliff House artifacts at auction and ran a well-attended pop-up museum in the old gift shop through 2022. The trademark donation means any future dispute over the building's identity is settled for good, and the sign is expected to return to the roofline as part of the new agreement.
China Beach Is Running Its Own Version of the Same Delay
A short walk from the Cliff House, at the end of Sea Cliff Avenue, the China Beach bathhouse tells the same story on a smaller scale. Built in 1957 and now in the process of seeking National Register of Historic Places status, the bathhouse has been effectively unusable for years, its restrooms and outdoor showers shut down, replaced by porta-potties that have become a fixture rather than a temporary measure.
The National Park Service and the Golden Gate National Parks Conservancy launched a feasibility study for the site back in 2017, and in 2023 announced a two-year rehabilitation project covering the retaining walls, the access road, the parking lot, a new accessible overlook, and eventually the bathhouse itself, with new restrooms, rinse-off stations, a rebuilt sundeck, and new quarters for the GGNRA's Ocean Rescue Patrol. The first half of that work went roughly to plan: the road, parking lot, and overlook were finished in 2024. The bathhouse renovation itself was the piece that stalled. The San Francisco Chronicle reported in March 2025 that the bathhouse work was only then set to begin, after a long delay, with construction expected to start that spring. By this summer, more than a year past that restart, the restrooms are still closed and the remodel is still described as ongoing.
So the beach that sits below some of the most expensive real estate in the city is now nine years into a project that began with a 2017 feasibility study, and the part of it people actually use every day, working restrooms and showers, is still not finished. The bathhouse work remains part of the rehabilitation project's timeline, following the road, parking lot, and overlook work completed in 2024.
The Trail and Other Open Coastal Features
Here is the part of the coastline that has nothing to do with leases or bid processes: the Lands End Coastal Trail itself. It runs along the old railbed of the Ferries and Cliff House Railway, past landmarks that remain open independently of the renovation projects. The trail leads walkers past the ruins of the Sutro Baths, out to the USS San Francisco Memorial near the trail's southern end, down a steep spur to Mile Rock Beach, and along the bluffs to Eagle Point, which borders Sea Cliff to the east. The Lands End Lookout Visitor Center, run by the Golden Gate National Parks Conservancy, sits above the old Cliff House site and stays open Friday through Monday.
The trail, visitor center, and coastal overlooks remain separate from the two building projects. Walks, views, and the sound of foghorns are part of the coastline experience regardless of those projects' schedules. Knowing which parts of the coastline are open and which are undergoing renovation can help readers plan a visit.
Signs of Progress to Watch Through 2026
These physical markers can help readers follow progress through the rest of 2026:
- The coffee and pastry shop in the old gift shop space is the piece most likely to open first, since it requires the least construction of the four planned concepts.
- The Cliff House sign returning to the roofline will be a visible, unmistakable signal that the trademark agreement has moved from paperwork to installation.
- Scaffolding coming down around the China Beach bathhouse will be a visible sign of progress on the renovation.
None of these are guarantees.
What is certain is that this stretch of Sea Cliff's coastline is genuinely different than it was two years ago, even if the difference so far is mostly in paperwork and property lines rather than open doors. The trademark question is settled. The road, parking lot, and overlook at China Beach are finished. For a neighborhood that has watched two of its most recognizable buildings sit empty for the better part of a decade, that counts as real movement.
If you're weighing what any of this means for property near the coastline, or simply want a clearer read on how these long-running public projects intersect with home values in Sea Cliff, Nob Hill Compass is glad to talk through what we're seeing on the ground. Request a Confidential Consultation whenever the timing is right for you.